1、石家庄铁道学院四方学院毕业论文 1 附录 A 英文原文 The engineering claims related theory The summary In this paper, the engineering claims related theory must research and engineering claims to the owner and the contractor classification and meaning between the claim to understand. 1.1 The engineering claims and the meani
2、ng and the claim classification The claim was in the project contract performance of the contract, one party because the other party fails to fulfill the obligations prescribed by the contract suffered losses, to the other party claim behavior. In practice, a claim is a two-way street, the construct
3、ion unit and the construction units may claim. Usually, claim means the contractor (construction unit) in the implementation of the contract, the causes of non-self engineering extension of time, cost and increase demand for the compensation of losses to the owner a claim. And the owner (the constru
4、ction units) for the construction unit shall bear the responsibility belongs to cause, and the actual loss happened, ask for compensation to the construction unit, called reverse claim for compensation. The nature of the economic compensation claims belongs to behavior, not punished. In the general
5、claim can negotiate way through friendly solution, if both sides cant reach a compromise, the dispute by arbitration can solve. Can claim from different angles, and according to the different standards of the following categories: (1)The cause of the classification Such as preparation for constructi
6、on, process control, quality control and cost control and management of causes of claim for compensation, this classification can explicitly pointed out that each and every one of the source of the claim, make the owner and engineers to audit analysis. (2) The purpose of the claim, according to clas
7、sification 石家庄铁道学院四方学院毕业论文 2 It can be divided into the time limit and expenses claims claim. Time limit is to ask the owner claims extended construction time, make the original provisions of the project completion date postpone so as to avoid the breach of the fine occurred; Cost is to ask the owne
8、r and the contractor claim the compensation fees loss and adjust the contract value. (3) According to claim the basis of classification It can be divided into the stipulations in the contract, the contract of the claim. The stipulations in the contract is to point to claim the claim involving conten
9、t in the documents to find the basis, the owner or the contractor can then put forward the claim. This claim is not so easy to dispute; The contract is the claim to the content of the claim involving in the documents without dedicated word narrative, but can according to the contract terms of some m