1、中文 3018 字 Comparison of Design and Analysis of Concrete Gravity Dam ABSTRACT Gravity dams are solid concrete structures that maintain their stability against design loads from the geometric shape, mass and strength of the concrete.The purposes of dam construction may include navigation, flood damage
2、 reduction,hydroelectric power generation, fish and wildlife enhancement,water quality,water supply,and recreation.The design and evaluation of concrete gravity dam for earthquake loading must be based on appropriate criteria that reflect both the desired level of safety and the choice of the design
3、 and evaluation procedures.In Bangladesh, the entire country is divided into 3 seismic zones, depending upon the severity of the earthquake intensity. Thus, the main aim of this study is to design high concrete gravity dams based on the U.S.B.R. recommendations in seismic zone II of Bangladesh, for
4、varying horizontal earthquake intensities from 0.10 g - 0.30 g with 0.05 g increment to take into account the uncertainty and severity of earthquake intensities and constant other design loads, and to analyze its stability and stress conditions using analytical 2D gravity method and finite element m
5、ethod. The results of the horizontal earthquake intensity perturbation suggest that the stabilizing moments are found to decrease significantly with the increment of horizontal earthquake intensity while dealing with the U.S.B.R. Recommended initial dam section, indicating endanger to the dam stabil
6、ity, thus larger dam section is provided to increase the stabilizing moments and to make it safe against failure. The vertical, principal and shear stresses obtained using ANSYS 5.4 analyses are compared with those obtained using 2D gravity method and found less compares to 2D gravity method, except
7、 the principal stresses at the toe of the gravity dam for 0.10 g - 0.15 g. Although, it seems apparently that smaller dam section may be sufficient for stress analyses using ANSYS 5.4, it would not be possible to achieve the required factors of safety with smaller dam section.It is observed during s
8、tability analyses that the factor of safety against sliding is satisfied at last than other factors of safety, resulting huge dam section to make it safe against sliding. Thus, it can be concluded that it would not be feasible to construct a concrete gravity dam for horizontal earthquake intensity g
9、reater than 0.30 g without changing other loads and or dimension of the dam and keeping provision for drainage gallery to reduce the uplift pressure significantly. Keywords: Comparison Concrete Gravity Dam Dam Failure Design Earthquake Intensity Perturbation Stability and Stress 1.Introduction Basic
10、ally, a gravity concrete dam is defined as a structure,which is designed in such a way that its own weight resists the external forces. It is primarily the weight of a gravity dam which prevents it from being overturned when subjected to the thrust of impounded water 1. This type of structure is dur
11、able, and requires very little maintenance. Gravity dams typically consist of a non overflow section(s) and an overflow section or spillway. The two general concrete construction methods for concrete gravity dams are conventional placed mass concrete and RCC. Gravity dams, constructed in stone mason
12、ry, were built even in ancient times, most often in Egypt, Greece, and the Roman Empire 2,3. However, concrete gravity dams are preferred these days and mostly constructed. They can be constructed with ease on any dam site, where there exists a natural foundation strong enough to bear the enormous w