1、英文文献 Highway asphalt pavement Preventive Maintenance Abstract: The high-grade highway asphalt pavement and damaged the various early stage disease, the type of damage and its causes, and made a crack repair, slurry seal asphalt pavement, such as preventive conservation technology. Key words: asphalt
2、 pavement; conservation asphalt pavement and the type of damage causes type of damage The asphalt pavement damage can be divided into: crack category, loose category, class and other types of deformation of the four major categories Causes (1) horizontal cracks in this relatively common disease, mai
3、nly due to contraction of asphalt surface temperature and semi-rigid or temperature shrinkage of the shrinkage caused. Roadbed degree of compaction less than this will lead to disease (2) vertical cracks in most cases took place in a half filled or half-dug embankment road widening, mainly from the
4、roadbed caused by uneven settlement. (3) cracking along its initial shape is round with a single trace or more of parallel vertical joints, gradually appeared in the horizontal or vertical Feng Jian oblique connection joints cracking form. Mainly due to lack of structural strength from the road (4)
5、along the road to track performance with a horizontal height difference, mainly because of foot-graded asphalt mixture design unreasonable. Poor or because of the stability of the grass-roots level and degree of compaction of the lack of construction so that the wheel tracks with the material and la
6、yer and grass-roots role in the traffic load has repeatedly appeared in the consolidation of lateral shear deformation and displacement caused. In addition, the overloading of heavy vehicles and also produce too many of the important reasons for rutting (5) is the main reason for the wave of road co
7、nstruction material design unreasonable or of poor quality, the road leading to insufficient material level of resistance Mou round of the role: Zongpo paragraph, because the high temperature will cause such diseases (6) loose water damage occurred mainly in the section on the serious. (7) pits is c
8、racked and loose, and other damage to the further development of the results. (8) embankment subsidence is mainly caused by insufficient degree of compaction, especially in some high-filling and compaction difficult to fill a half-dug sections and structures at both ends of a (9) If the spalling asp
9、halt Mixture using neutral or acid stone, will cause aggregate and asphalt adhesion b s (10) Fan You asphalt Mixture too much asphalt content, porosity smaller, high temperature stability poor, is the main reason for a Fanyou asphalt pavement Preventive Maintenance Technology Asphalt Pavement Preven
10、tive Maintenance Technology: repair cracks, slurry seal, the closure of the Stone Chip, the closure of the table and micro-thin heat Overlay (including open-graded, Miji and with intermittent grading). Here focus of slurry seal and repair cracks in technology. repair cracks in technology and methods
11、 slotted repair method Slotted repair method for small and medium-sized cracks. Crack is a better approach. The equipment used slot machines and irrigation sewing machine to make up for joint use of materials designed specifically for repairing cracks in the sealed plastic (polymer modified asphalt)
12、, slotting size of at least l cm wide, l 3 cm deep. Slotted than the depth should not exceed 2: l, greater depth than the smaller the better. Slotted repair of the construction process are as follows: preparations for the inspection slot machines and irrigation sewing machine to ensure that its tech
13、nical condition: Pavement cracks under the specific circumstances to determine fill slit design: sewing machine and start filling the tank sealant heating add sealant, sealant heating , Stirring to l90 , can not exceed 200 ; heating during the sewing machine Tuogua irrigation in the truck behind, an
14、d the sealant, Geli Dun, the umbrella label instructions, and Shoulder-style slot machines, such as hair dryer mounted on trucks, Shi T locations scheduled to drag on a safe highway maintenance of order (JTG H30-2004) as the provisions of the construction area operations. slotted in accordance with
15、the design of the slot size, good pre-conditioning F-slot machine slot depth, and then slotted operations, operations, according to crack width type of situation, timely adjustment slotted sizes to meet the minimum design requirements. Shoulder-to-trough hair dryer to bed and cracks on both sides of
16、 the ejecta l0 till at least within the scope of cleaning dust thoroughly clean. irrigation in the seam if the temperature below the 4:00-slit. Irrigation with a sewing machine to be slotted parts of the preheating equipment for preheating, if not at this temperature preheat to fill the joints, seal
17、ants would reduce the cohesive force: if the temperature higher than the 4 at the joint meeting, From time to preheat, the general meeting of the joint after preheating better results, in sealed plastic heating temperature reached about 190 , with irrigation with a sewing machine for pressure nozzle