1、山东建筑大学 毕业 设计 外文文献及译文 - 1 - 外文文献: GRAPHICAL-BASED MULTISTAGE SCHEDULING METHOD FOR RC BUILDINGS Y. C. HUANG Department of Construction Management, Hwa Hsia Institute of Technology and Commerce, 111 Hwa Hsin Street,Chung Ho City, Taipei Hsien, Taiwan, Republic of China Received 13 February 2004; accep
2、ted 4 March 2005 In Taiwan, contractors are becoming specialized in certain types of construction in an increasingly competitive environment and this specialization requires some scheduling models to provide better scheduling results for each type of construction. A new practical method, Graphical-B
3、ased Multistage Scheduling Method (GMSM),for scheduling RC building superstructures is presented herein. From the analysis of characteristics and construction custom of RC buildings, four constraints, (a) downup construction, (b) building inspection, (c) reuse of beam forms, and (d) reuse of slab fo
4、rms, can be established. The GMSM is developed utilizing a graphical-based method and the concept of resource reuse, and the general form of the GMSM to be facilely implemented in any worksheet software is derived as well. The results of this study provide some quantitative information as a useful g
5、uide for scheduling RC building superstructures. Keywords: Multistage scheduling, repetitive project, RC building, GMSM Introduction In Taiwan, contractors are becoming specialized in certain types of construction in an increasingly competitive environment and this specialization requires some sched
6、uling models to provide a better scheduling for each type of construction. The majority of high-rise buildings located in urban areas in Taiwan are RC structures. It is deemed crucial for high-rise buildings that a scheduling model for this type of construction can not only increase profits but also
7、 reduce the impact on urban traffic. Of the high-rise buildings constructed to date, the network planning technique has been 山东建筑大学 毕业 设计 外文文献及译文 - 2 - commonly adopted in scheduling. The Critical Path Method (CPM) is the most popular one; for instance, prevalent scheduling software such as MS Proje
8、ct, Primavera Project Planner, etc., were developed based on CPM. However, assuming that all activities are independent, the CPM does not take into consideration the resource reuse where there is repetition of identical activities on every floor. OBrien (1975) proposed that high-rise building be div
9、ided into two categories: (1) non-repetitive works, such as earthworks, foundations, and non-typical floor plans; and (2) repetitive works, such as superstructures with standard floor designs. In the former category, CPM is utilized to execute scheduling. For the latter, a scheduling model suitable
10、for repetitive construction has to be developed. Reda (1990) and Cole (1991) also demonstrated the necessity of scheduling for repetitive projects. This study, according to OBriens suggestion, is to develop a graphical-based scheduling method applicable to repetitive projects of RC building superstr
11、uctures so that the most popularly practiced construction method in Taiwan, sitecast concrete structures with wooden forms, may be in line with it. Literature reviews The theoretical scheduling approach of repetitive projects is based on the principle of Assembly Line Balance, in which there are two