1、 1 Using Weibull Analysis for Evaluation of Cost and Schedule Performance Khaled M. Nassar1; Hordur G. Gunnarsson2; and Mohamed Y. Hegab, P.E.3 Large amounts of money are lost each year in the construction industry because of poor schedule and cost control. Few contractors specify and follow systema
2、tic schedule monitoring practices. Traditionally, the earned value method EVM is used to control and monitor schedule performance using the schedule and cost performance indices which compare the budgeted cost of work performed to what was originally scheduled or what is actually expended. This pape
3、r presents a statistical approach, namely Weibull analysis, to evaluate stochastically the schedule performance of construction or design projects. The approach can be used in conjunction with the EVM to enhance the evaluation and control of schedule performance. Weibull analysis is a common method
4、for failure analysis and reliability engineering used in a wide range of applications. In this paper, the applicability of Weibull analysis for evaluating and comparing the reliability of the schedule performance of multiple projects is presented. The various steps in the analysis are discussed alon
5、g with an example in which two projects are analyzed and compared. The authors conclude that Weibull analysis has several advantages and provides a relatively robust and effective method for construction managers to better control and monitor their projects. Construction projects are seldom on-sched
6、ule all the time. The amount of work performed on the project usually fluctuates from one period to the other. In fact, according to the 80 / 20 rule. suggested by the 18th Century economist, Pareto 80% of the effort will be expended during 20% of the project duration. This creates a significant pro
7、blem in trying to monitor the actual performance of the project schedule and specifically trying to decide whether or not the project can finish on time., the reliability of the project schedule performance .The earned value method EVM is often used as a project control technique to provide a quanti
8、tative measure of schedule performance. In the EVM, the schedule and cost performance indices C/SPI are used for constant monitoring of the projects cost and schedule based on an original critical path method CPM schedule Chang 2001 . Unfortunately, CPM scheduling in general creates an unrealistic e
9、xpectation regarding project schedule performance. Starting a project one day and expecting that the project will finish on an exact date some two or three years in the future is unrealistic. Therefore, there is a need to extend schedule analysis techniques, like the EVM, to provide means for probab
10、ilistically analyzing the schedule performance and measuring the risks involved. In other management domains like software projects and business management, tools from the area of reliability, availability, and maintainability RAM engineering are now used to predict and avoid sudden system failures
11、. RAM engineering is emerging as the newest discipline in product development due to new accurate, quantitative methods. Weibull analysis is foremost among these tools . Weibull analysis is a widely used method in the field of manufacturing and industrial engineering. It has mainly served for simula
12、ting failure rates or lifetime of certain products. By using this particular analysis one can make predictions about products life, compare the reliability of competing product designs, and manage spare parts inventories to name a few common industrial applications Dorner 1997, 1999 . The objective
13、of this study is to discuss and present the applicability of Weibull analysis for evaluating schedule performance using cost and performance indices C/SPI and to provide construction 2 managers with an effective tool for stochastically evaluating the C/SPI. A number of probabilistic techniques were
14、checked against the data using Anderson-Darling measure AD value and the Weibull distribution was found to be the best representative for evaluating schedule performance and cost performance having the lowest AD value . In this paper, an example is provided, in which two projects are compared and an
15、alyzed. The first part of this paper briefly covers the EVM and performance indices. The second part discusses the Weibull distribution, it sharacteristics and its application to EVM. This is followed by an example of Weibull analysis using actual data of C/SPI, in which two projects are compared. L
16、astly, conclusions are drawn. Earned Value Method and Performance Indices The goal of the EVM is to control costs and schedule performance during the project. This is accomplished by calculating a number of measures. First, the budgeted cost for work scheduled BCWS within a given time period is calc