1、外文文献: Risk Analysis of the International Construction Project By: Paul Stanford Kupakuwana Cost Engineering Vol. 51/No. 9 September 2009 ABSTRACT This analysis used a case study methodology to analyse the issues surrounding the partial collapse of the roof of a building housing the headquarters of t
2、he Standards Association of Zimbabwe (SAZ). In particular, it examined the prior roles played by the team of construction professionals. The analysis revealed that the SAZs traditional construction project was generally characterized by high risk. There was a clear indication of the failure of a con
3、tractor and architects in preventing and/or mitigating potential construction problems as alleged by the plaintiff. It was reasonable to conclude that between them the defects should have been detected earlier and rectified in good time before the partial roof failure. It appeared justified for the
4、plaintiff to have brought a negligence claim against both the contractor and the architects. The risk analysis facilitated, through its multi-dimensional approach to a critical examination of a construction problem, the identification of an effective risk management strategy for future construction
5、projects. It further served to emphasize the point that clients are becoming more demanding, more discerning, and less willing to accept risk without recompense. Clients do not want surprise, and are more likely to engage in litigation when things go wrong. KEY WORDS:Arbitration, claims, constructio
6、n, contracts, litigation, project and risk The structural design of the reinforced concrete elements was done by consulting engineers Knight Piesold (KP). Quantity surveying services were provided by Hawkins, Leshnick & Bath (HLB). The contract was awarded to Central African Building Corporation (CA
7、BCO) who was also responsible for the provision of a specialist roof structure using patented “gang nail” roof 外文文献及译文 20100710 - 1 - trusses. The building construction proceeded to completion and was handed over to the owners on Sept. 12, 1991. The SAZ took effective occupation of the headquarters
8、building without a certificate of occupation. Also, the defects liability period was only three months . The roof structure was in place 10 years before partial failure in December 1999. The building insurance coverage did not cover enough, the City of Harare, a government municipality, issued the c
9、ertificate of occupation 10 years after occupation, and after partial collapse of the roof . At first the SAZ decided to go to arbitration, but this failed to yield an immediate solution. The SAZ then decided to proceed to litigate in court and to bring a negligence claim against CABCO. The preparat
10、ion for arbitration was reused for litigation. The SAZs quantified losses stood at approximately $ 6 million in Zimbabwe dollars (US $1.2m) . After all parties had examined the facts and evidence before them, it became clear that there was a great probability that the courts might rule that both the
11、 architects and the contractor were liable. It was at this stage that the defendants lawyers requested that the matter be settled out of court. The plaintiff agreed to this suggestion, with the terms of the settlement kept confidential . The aim of this critical analysis was to analyse the issues su
12、rrounding the partial collapse of the roof of the building housing the HQ of Standard Association of Zimbabwe. It examined the prior roles played by the project management function and construction professionals in preventing/mitigating potential construction problems. It further assessed the extent
13、 to which the employer/client and parties to a construction contract are able to recover damages under that contract. The main objective of this critical analysis was to identify an effective risk management strategy for future construction projects. The importance of this study is its multidimensio
14、nal examination approach. 外文文献及译文 20100710 - 2 - Experience suggests that participants in a project are well able to identify risks based on their own experience. The adoption of a risk management approach, based solely in past experience and dependant on judgement, may work reasonably well in a sta
15、ble low risk environment. It is unlikely to be effective where there is a change. This is because change requires the extrapolation of past experience, which could be misleading. All construction projects are prototypes to some extent and imply change. Change in the construction industry itself sugg
16、ests that past experience is unlikely to be sufficient on its own. A structured approach is required. Such a structure can not and must not replace the experience and expertise of the participant. Rather, it brings additional benefits that assist to clarify objectives, identify the nature of the unc
17、ertainties, introduces effective communication systems, improves decision-making, introduces effective risk control measures, protects the project objectives and provides knowledge of the risk history . Construction professionals need to know how to balance the contingencies of risk with their speci
18、fic contractual, financial, operational and organizational requirements. Many construction professionals look at risks in dividually with a myopic lens and do not realize the potential impact that other associated risks may have on their business operations. Using a holistic risk management approach
19、 will enable a firm to identify all of the organizations business risks. This will increase the probability of risk mitigation, with the ultimate goal of total risk elimination . Recommended key construction and risk management strategies for future construction projects have been considered and the
20、ir explanation follows. J.W. Hinchey stated that there is and can be no best practice standard for risk allocation on a high-profile project or for that matter, any project. He said, instead, successful risk management is a mind-set and a process. According to Hinchey, the ideal mind-set is for the parties and their representatives to, first, be intentional about identifying project risks and then to proceed to develop a systematic and comprehensive